Whats completed, what's not, at Petronas USD27B PIC complex

Whats completed, what's not, at Petronas USD27B PIC complex
WESPECH PTE LTD
8 Eu Tong Sen Street #14-94, The Central, Singapore (059818)
+65 315 904 24

29.01.2018

MOSCOW (MRC) -- Petroliam Nasional Bhd (Petronas) shared the breakdown of development progress of its USD27 billion Pengerang Integrated Complex (PIC) here yesterday, which was 84% completed as at end-December 2017, as per Hydrocarbonprocessing.Petronas' 300,000 bpd refinery complex, which forms part of the USD16 billion RAPID project within the 6,242-acre PIC, was at 94% development comp

Full article at mrcplast.com